ps8474272 ps8474272
  • 01-03-2021
  • Mathematics
contestada

if 9 people can do a piece of work in 90 days then how many days 19 people will take to complete the same piece of work​

Respuesta :

rmroomi2
rmroomi2 rmroomi2
  • 01-03-2021

Answer:

190 days

Step-by-step explanation:

cross multiply

19×90=1710

1710/9=190

Answer Link

Otras preguntas

Which of the following plants is classified as decorative foliage? A. Liatris B. Star-of-Bethlehem C. Euphorbia D. Aspidistra
n/5=10. x/1=9 a/5=3 c/7=9 i need to know what the variables are
Will use us 3/4 cup of olive oil to make three batches of salad dressing how much oil does will use for one batch of salad dressing
Where do earthquakes usually occur?
Tunis is a free port in Morocco.
What happened during the middle ages⇒what caused the change⇒what happened during the renaissance ? please do bullet points
how do you convert units in length?
____________ occurs when heat is transferred to an object through direct contact with particles; an example would be the heat from a stove transferring to your
Which word means "an excess" or "an overabudance in supply?
Showing empathy is only necessary if you want lots of friends.