12 workers can do a peice of work in 20 days. How many workers should be added to complete work in 16 days?​

Respuesta :

atchleyamirah69
atchleyamirah69 atchleyamirah69
  • 01-04-2021
3 workers

if 12 workers can do a piece of work in 20 days, then one person can do it in 240 days. 240/16 is 15. That is the number of workers that you need in total to it in 16 days. Since the question ask how many more workers,
15 - 12 = 3 more workers.
Answer Link

Otras preguntas

good evening! Can someone please answer this, ill give you brainliest and your earning 50 points. Would be very appreciated.
Which of the following statements are TRUE? SELECT ALL THAT APPLY.
Scientists studied a deer population for 10 years. They generated the function f(x) = 248(1. 15)x to approximate the number of deer in the population x years af
How did F. W. de Klerk influence change in South Africa?
How did F. W. de Klerk influence change in South Africa?
Question 7 (2 points) What is the equilibrium price for backpacks? Annual Supply and Demand for Backpacks (in Thousands) Price Quantity Demanded Quantity Suppli
a circular flower bed is 20 meters in diameter and has a circular sidewalk around it that is 3 meters wide . find the area of the sidewalk in square meters . us
He is old and has a stump for a hand.
There are two unit rates for every rate, true or false?
Help me please!!!!!!!!!