15 workers working 8hrs a day can complete a piece of work in 20 days. In how many days will 10 workers do it,working 6 hrs a day? please help!!

Respuesta :

ridmitharuka
ridmitharuka ridmitharuka
  • 02-08-2021

Answer:

40 days

Step-by-step explanation:

w1*h1*d1=w2*h2*d

15*8*20=10*6*d

2400=60d

d=2400/60

d=40

Answer Link

Otras preguntas

Marcus needs to rewrite f(x) = x2 + 6x + 4 in vertex form. His answer is f(x) = ()2 – 5.
This country was the cite of the 1994 genocide of ethnic Tutsi people by Hutu people.
Using "Hace que" structure taught in this lesson,Tell how long ago it has been since you took a trip. Then tell where you went and what you did there. plz make
can some one help me with this will give brainliest
Write a balanced chemical equation for the standard formation reaction of solid mercury(ii) oxide .
When limestone (calcium carbonate) is strongly heated, it breaks down into calcium oxide and carbon dioxide. If 88 grams of carbon dioxide is released when 20
Which graph represents the solution set for the inequality x ≤ 18?
X+23=-23 solve for x pls help !!!!
Use the table provided to determine the total amount paid on a 30 year fixed loan, at 6.0%, of $75,000. $162,000 c. $143,820 b. $153,750 d. $133,250
Geometry help please!