Jin schedules 496 hours for a project. He plans to work 8 hours each day. How many days will it take to complete the project?​

Respuesta :

penguinlife90 penguinlife90
  • 01-12-2021

Answer:

62 days

Step-by-step explanation:

496/8 = 62

Answer Link
clickykeyboardasmr
clickykeyboardasmr clickykeyboardasmr
  • 01-12-2021

496/8=62

Hope this helps!

Answer Link

Otras preguntas

3897 rounded to nearest ten
Name three services provided by the black church before the civil war
If the value of static friction for a couch is 400N, what could be a possible valueof its kinetic friction?​
Chordate pharyngeal slits appear to have functioned first as
What is 2 2/3 + 1 1/2
Study the image taken during World War I. This image was originally published in an American encyclopedia after the war. Who is the intended audience of this ki
Sue has 18 sweets. Tony also has 18 sweets. Sue gives Tony x sweets. Sue then eats 5 of her sweets. Tony then eats half of his sweets. Write expressions for the
Who does Hamlet want to be king after he is gone?
I will give u brainliest no cap if u help me
How has the ride of oxygen changed life on planet Earth ?