If 24 electricians can wire some new houses in 15 days, how many electricians would be required to do the job in 12 days?.

Respuesta :

shishirshrestha989
shishirshrestha989 shishirshrestha989
  • 04-01-2022

Answer:

here,

electrician/days

24 - 15

x(let). -12

direct proportion,

then,

exchange X up 24 down

or,24*15=12*X

or,24*15divided by 12=X

X=30

hence,30 electrician required to do complete in 12 days

Answer Link

Otras preguntas

Use the figure below list the sides greatest to least of triangle RMP. PR, MP, MR MP, PR, MR MR, MP, PR MR, PR, MP
Luke is 5 feet 11 inches and weighs 170 pounds. Using the body mass index chart as a guide, under which category would he fall? A- underweight B- normal C- over
Khianna wants to make a batch of her Grandma chocolate chip cookies from a friend. The recipe is shown on the recipe card below ( in the photo) She realizes she
Courts generally use the​ ________ when determining the value of human life in wrongful death suits.
can someone please help me!!! thanks
passes through (3,5) and (-1,5)
Melisma is when.......
Which type of lodging is most economical? hotel motel hosteria albergue
Find the 8th term of the sequence which has a first term of 10 and has a common ratio of 1.75 round you're answer to the nearest hundredth if necessary.A. 164.1
Which statements are true about the linear inequality y > 3/4x – 2? Check all that apply. [ ] The slope of the line is –2. [ ] The graph of y > 3/4x –